Industry Brewery
Capacity 3,120 m3/day Surface Water Treatment Plant
Scope of Work • Detailed Engineering Design, Procurement and Installation of UF Membrane skids, pump skids, Backwash Recovery System, holding tanks, Stainless Steel Activated Carbon Filter, chemical dosing equipment and tanks
• Skids and tanks are fabricated in KL & shipped to Uganda for hookup and commissioning
Portfolio Item

Overview of Water Treatment Plant

Description
Country Mbarara, Uganda
Industry Brewery
Capacity 3600 m3/day Surface Water Pretreatment System)
Scope of Work • Detailed Engineering Design (Process, Mechanical, Electrical and Civil)
• High Turbidity Surface water treatment (50 – 200 NTU)
• High iron loading with associated silt and organic loading
• Raw Water Collection in panel tanks
• Pre-chlorination and chemical treatment using rapid coagulation and flocculation
• High Rate precipitation clarifier in bolted steel construction with engineered supports, internals and tube settler media
• Chemical makeup and dosing systems
• Skid mounted pumps sets equipped with intelligent automation
• Sludge Treatment System with Automated Polymer Preparation and Dosing Unit and Semi-automatic Plate and Frame Type Filter Press
Portfolio Item

Secondary Clarifier Construction in GFS Bolted Steel Material

Description
Country Tanzania, Dar Es Salaam
Industry Brewery
Capacity 4800 m3/day Groundwater Treatment Plant
Scope of Work • Detailed Engineering Design (Process, mechanical, electrical and automation design)
• Brackish Groundwater pre-treatment for brewery using ultrafiltration technology
• Treatment scheme includes ground water collection and storage, coarse filtration and absolute filtration using Ultrafiltration membrane, disinfection, chemical dosing and backwash recovery system
Portfolio Item
Description
Country Mwanza, Tanzania
Industry Brewery
Capacity 100 m3/day Backwash Recovery System
Scope of Work • Detailed Engineering Design, Procurement and Installation of a 20 ft containerized treatment system
• Treatment system includes waste water collection and storage, chemical treatment, clarification and multimedia filtration
• Backwash, and rinse recovery from carbon, media filters and ultrafiltration systems to improve water quality
• Container, skids & tanks are fabricated, pre - assembled and tested in KL prior to shipment to Mwanza
• Chemical makeup and dosing systems
• Skid mounted pumps sets equipped with intelligent automation
• Sludge Treatment System with Automated Polymer Preparation and Dosing Unit and Semi-automatic Plate and Frame Type Filter Press m
Portfolio Item
Description
Country Selangor, Malaysia
Industry Brewery
Capacity 2,400 m3/d groundwater treatment Plant
Scope of Work • Upgrade of existing treatment plant to treat 100 m3/hr of groundwater
• New treatment system includes UV disinfection system, new high pressure pumps and additional RO pressure vessels
• Existing RO skid is modified by introducing new instruments and automations
Portfolio Item
Description
Country Arusha, Tanzania
Industry Brewery
Capacity 100 m3/day Backwash Recovery System
Scope of Work • Detailed Engineering Design, Procurement and Installation of a 20 ft containerized treatment system
• Treatment system includes wastewater collection and storage, chemical treatment, clarification, backwash and rinse recovery from activated carbon filters and ultrafiltration systems to improve water quality
• Container, Skids & tanks are fabricated, pre - assembled and tested in KL prior to shipment • Chemical makeup and dosing systems
• Skid mounted pumps sets equipped with intelligent automation
• Sludge Treatment System (Holding tank, polymer dosing system and filter press)


Description
Country Mbarara, Uganda
Industry Brewery
Capacity 120 m3/day Brewery Effluent Recycle Pilot Plant
Scope of Work • Design and build a containerized membrane pilot plant for brewery effluent
• The pilot plant is equipped with UF membrane system, CIP/CEB systems, and extensive automation for data collection


Description
Country Dar Es Salaam, Tanzania
Industry Brewery
Capacity 4,800 m3/day Upgrading of TBL Water Treatment Plant at DSM (Phase 2)
Scope of Work • Detailed Engineering Design, Procurement and Installation of Water Treatment Plant with UF and CIP systems and extensive automation for data collection
• Skid mounted equipment are fabricated in KL and shipped to site
Portfolio Item
Description
Country Mbarara, Uganda
Industry Brewery
Capacity 15 m3/hr Hot Water Sanitization (HWS) System
Scope of Work •Detailed Engineering Design, Procurement and Installation of HWS system for brewery water sanitization
Portfolio Item
Description
Country Nigeria, West Africa
Industry Brewery
Capacity 85 m3/hr Water Treatment Plant
Scope of Work • Detailed Engineering Design, Procurement and Installation of Water Treatment Plant with UF, RO, CIP and CEB systems
• Plant is equipped with extensive automation for data collection
• Skid mounted equipment are fabricated in KL and shipped to project site
Portfolio Item